Pipeline Integrity Support- LNG as Primary Feed

Application: Distribution Integrity Management- Pipeline Outage

Duration: 15 Days

Fuel Type: LNG

Flow Rate: 20-40 MCFH

Equipment: 2-Queens (1115 MCF), 1-LNG Transport (800 MCF), 2-Forced Air Vaporizers

Situation: Thigpen Energy provided natural gas to a regulator station at a flow rate of 20-40 MCFH. Customer requested our services to hold up a town border while they were performing pipeline integrity testing on their line. The mainline is required to be blown down to make repairs as required by their DIMP program.  The town was provided LNG for the duration of the project, keeping all customers whole.